Client Case Details
As a German sports brand with a history of nearly one hundred years, since its birth in the 1920s, it has always stood in the brand camp of sports goods in the world as a "leader", and has always been a member of all levels of the sports world, providing top level sports shoes, sportswear and accessories. Headquartered in Germany, it has nearly 150 wholly-owned subsidiaries and joint ventures worldwide and more than 10000 retail stores nationwide.
background
In the past 20 years, increasingly wealthy Chinese consumers, fashionable and modern youth groups and the Beijing Olympic Games have all helped Party A to make great progress in China, and China has become the second largest market of Party A in the world
In March 2018, Party A announced to integrate the four key regions with strong growth in Greater China, Japan, South Korea, Southeast Asia and the Pacific into a unified Asia-Pacific market
In 2016, a wholly-owned company was established to provide IT system platform to different subsidiaries of the Group;
From 2020, with the rapid development of business in China, Party A formally controls the joint venture securities company and begins to re-plan the network architecture and IT infrastructure of all subsidiaries in China
2019 Asia-Pacific headquarters weak current integration
1. The new headquarters has a total of 21 floors, with an available office area of more than 30000 square meters, to meet the needs of office network and telephone for more than 1500 employees. Realize flexible, efficient and orderly office automation and business management.
2. There are more than 4000 network information points, 38 optical fibers, more than 400 APs, 30 cabinets, 19 UPS, environmental monitoring and distribution systems.
3. Coordinate with customer IT, project management company, general contractor and other relevant parties to complete the whole project as scheduled.
Suzhou Logistics Automatic Distribution Center will be newly established in 2020
1. The intelligent operation center is located in the Pross Logistics Park, with a building area of about 120000 square meters. A total of 4 warehouses and 1 office building network information point construction, more than 600 APs, 5 UPS, 10 air conditioners, environmental monitoring and distribution systems.
2. Coordinate with customer IT, project management company, general contractor and other relevant parties to complete the whole project as scheduled
2019 – now: National data center maintenance service
Customers outsource the data center and wiring maintenance to GD:
GD provides daily on-site maintenance and hardware maintenance services for the computer room environmental equipment (UPS, air conditioning, environmental monitoring, etc.) in Beijing, Shanghai, Dalian, Tianjin, Chengdu, Guangzhou and Shenzhen to ensure the stability of the computer room environment, and arrives at the site 24 hours 7 days to deal with problems.
2022 Tianjin warehouse wiring transformation service
In 2022, the Tianjin warehouse will renovate the wiring, adding 220 network points and 70 AP points